On this page you will find descriptions and pictures of our current year's projects.
Focus: To improve drainage off the road of the Barry street corridor.
Update August 24th Working on Storm structures today west side of street
Update August 25 Tuesday Halfway done with structures on West side of street heading down southwest side tomorrow.
Update Sept 1, 2026, West side of Barry Street structure and pipe installation complete. Back fill completed and 85% completion to subgrade. We will be starting east side fo Barry running from North to South Tuesday Sept 8 7 am. Everyone should have recieved the letter for sump pump hook ups to manholes, any questions please call us. Thanks and have a great holiday weekend.