On this page you will find descriptions and pictures of our current year's projects.
Focus: To improve drainage off the road of the Barry street corridor.
Please see attached information letter
Project Start Date 7-29-26
West Side of Barry Houses -7-29-26 Aprons Removed-Please Park cars and garbage cans on east side of street. Starting 8 a.m.
Monday July 27 Update- Layout has started with lath wood stakes. Please do not disturb or remove these during project.
JULIE has located all the utilities do not disturb their marks or flags please as they let us know critical utility placement.
We began precutting driveways we will let you know when we will actually be removing the material from them.
We are starting with Crossover work on the north side of the street.
Due to material issues structures and pipe will be starting around next Wednesday.
NEW UPDATE: Wednesday July 29
Due to the significant storm damage this project has been delayed until the week of August 3rd crews will be working on the project thank you for your patience.
NEW UPDATE Monday August 3
We will be starting this Wednesday on the north end of the street working on the underground.

Please see attached information of proposed new storm system being installed.